Calmac Ferries Limited

Office 365 Migration

Incomplete applications

19
Incomplete applications
14 SME, 5 large

Completed applications

18
Completed applications
15 SME, 3 large
Important dates
Opportunity attribute name Opportunity attribute value
Published Tuesday 19 March 2019
Deadline for asking questions Tuesday 26 March 2019 at 11:59pm GMT
Closing date for applications Tuesday 2 April 2019 at 11:59pm GMT

Overview

Overview
Opportunity attribute name Opportunity attribute value
Summary of the work CFL wish to implement a phased migration approach to the current IBM Lotus Notes / Domino / SmartCloud email and Connections collaboration tools set to Microsoft’s Office 365. CFL are looking to procure professional services from a suitable and qualified IT Partner who will work with the internal project team
Latest start date Friday 24 May 2019
Expected contract length
Location Scotland
Organisation the work is for Calmac Ferries Limited
Budget range

About the work

About the work
Opportunity attribute name Opportunity attribute value
Why the work is being done CFL are looking to migrate the current IBM Lotus Notes / Domino / SmartCloud email and Connections collaboration tools set to Microsoft’s Office 365. In order to assist with the migration CFL are looking to procure professional services from a suitable and qualified IT Partner who will work with the internal project team to deliver their requirements
Problem to be solved To provide sufficient detail to enable commencement of the procurement approach for the migration of Office 365 from IBM Lotus Notes / Domino / Smartcloud, Connections .
Who the users are and what they need to do • Configuration of approx. 1850 users and shared mailboxes,
• Coexistence design,
• Migration design and planning,
• Migration & coexistence implementation,
• Functionality testing of O365, Exchange, Teams & client connectivity,
• Migration of early adoption programme – IT and an agreed business department,
• Migration of 1 x Cohort,
• Project Management of agreed partner deliverables,
• Call off technical support days,
• Skills transfer to IT department
Early market engagement
Any work that’s already been done
Existing team CFL IT Department
Current phase Not applicable

Work setup

Work setup
Opportunity attribute name Opportunity attribute value
Address where the work will take place Gourock and their location
Working arrangements As required
Security clearance

Additional information

Additional information
Opportunity attribute name Opportunity attribute value
Additional terms and conditions

Skills and experience

Buyers will use the essential and nice-to-have skills and experience to help them evaluate suppliers’ technical competence.

Skills and experience
Opportunity attribute name Opportunity attribute value
Essential skills and experience
  • Relevant Office 365 migration skills
  • Relevant IBM migration skills
Nice-to-have skills and experience Managing business change

How suppliers will be evaluated

How suppliers will be evaluated
Opportunity attribute name Opportunity attribute value
How many suppliers to evaluate 3
Proposal criteria
  • Technical solution
  • Approach and methodology
  • Value for money
Cultural fit criteria Work as a team
Payment approach Capped time and materials
Assessment methods Written proposal
Evaluation weighting

Technical competence

50%

Cultural fit

20%

Price

30%

Questions asked by suppliers

Questions asked by suppliers
Supplier question Buyer answer
1. Does CFL have the technical resource to carry out the migration and consultancy is required from supplier or the whole team to carry out the migration? We have the technical resource to complete the migration but would look for the supplier to complete a proof of concept, small pilot and 1 x live migration. We would expect the supplier to train the internal staff to complete the remaining migrations and provide some professional service days as a point of escalation.
2. Coexistence implementation" – How long does O-365 and IBM need to co-exit? Only till all users are migrated or beyond it?
You must publish the question with your answer on the ‘Office 365 Migration’ page by Monday 1 April 2019 at:
Only until all users are migrated
3. What roles are available in the existing team? Notes administrator
Infrastructure Lead
Data migration lead
Enterprise Architect
PM
Business Change Lead
Test Lead
4. May I know if there is any budget in mind? We will not be publishing budget figures.
5. What is the budget for this project? We will not be publishing budget details.
6. Will third-party tools used for migration/cloud-connectivity etc. be included in the price of proposal or are these separate? We would expect the supplier to provide the cost for the supply, configuration and testing of the migration tools
7. How many specalists are expected for this position? Not sure what is meant by this question, we would expect the supplier to use how many as required.
8. Which version of "IBM Lotus Notes / Domino / SmartCloud email and Connections collaboration tools set" is in use at CFL. If different versions are used by different users, please let us know the oldest version nad the newest version being used. BM Lotus Notes Client 9.0.1.13294 -
Domino on Premise 9.0.1 (Fix pack version may vary) - Domino Servers

Don't have any Smart Cloud versions as its the cloud. We have access to online email and Verse clients. Notes Client used to access email in the cloud also.
IBM Connections Plugin 17.05 - IBM Connections Collaboration

Hybrid Environment.

The Domino servers should be out of scope as we are not doing anything to these. We will need the Notes Client for CPS, not sure if we want to use the notes 10 client or leave as is ?
9. Which version of "IBM Lotus Notes / Domino / SmartCloud email and Connections collaboration tools set" is in use at CFL. If different versions are used by different users, please let us know the oldest version nad the newest version being used. BM Lotus Notes Client 9.0.1.13294 -
Domino on Premise 9.0.1 (Fix pack version may vary) - Domino Servers

Don't have any Smart Cloud versions as its the cloud. We have access to online email and Verse clients. Notes Client used to access email in the cloud also.
IBM Connections Plugin 17.05 - IBM Connections Collaboration

Hybrid Environment.

The Domino servers should be out of scope as we are not doing anything to these. We will need the Notes Client for CPS, not sure if we want to use the notes 10 client or leave as is ?
10. Do you have a target completion date in mind for this project? Target completion date is End of December 2019
11. In terms of platform co-existence. Are you looking for full functionality i.e. calendar shares? Yes full functionality
12. Would you expect the supplier to be full-time on-site or is there scope for remote activity? There will be a requirement to be on site for technical workshops etc but remote activity would be okay in some instances.
13. Are there multiple locations needing support or would it be one central location from where the work will be carried out ? The deployment will be from one central location Gourock but will be to multiple locations. It is expected that the supplier will be responsible for the procurement, configuration, testing, Proof of concept and deployment to 1 x live site then the internal team will be responsible for the migration to the other sites.
14. What is the scope of the PoC and Pilot ? Also, how many users are planned for the first live migration ? The PoC will be up to 5 users single site shore based cloud to cloud & 5 users major vessel on prem to cloud, pilot will be shore based cloud to cloud up to 20 users and on prem to cloud a major vessel and live migration cloud to cloud 40 users
15. Please confirm who the people on your selection panel are and their individual roles and responsibilities We will have a project team but will not publish their names. They will represent the relevant areas of the business.
16. Can you please specify the budget range allocated for the system integration of the CRM project? This has still to be fully defined
17. Which Smartcloud collaboration tools are in use in CFL, and in scope for migration (in addition to Verse email) e.g.:
a. Communities?
b. Content management (including any links to external services)?
c. Chat?
d. Meetings?
a. Communities? Yes
b. Content management (including any links to external services)? No
c. Chat? Yes
d. Meetings? Yes
18. Is the coexistence scope limited to mailbox objects (e.g. email, calendars, distribution groups, rooms and resources, etc)? Yes
19. The project target completion date is end December 2019. Is there target completion date for the POC, Pilot and Cohort 1? No that is the project completion date
20. Do CFL have infrastructure capacity and licensing required to add servers and storage for a migration/coexistence environment, or should the cost of additional infrastructure be included in any proposal? There is no requirement for additional Migration hardware as the existing server infrastructure will be used.